Sunday, September 27, 2009

Getting ready for the tower and cabling

This week the people that place little flags to mark the electric and phone lines will be coming. This is to make sure that we don’t dig in the wrong area for the wind turbine foundation and the underground cables to attach to the inverter.

It is also time to get insurance. I talked to my insurance company back in February when I started this project.

One article on the net that I found helpful on insurance was this one by Mick Sagrillo, Sagrillo Power & Light


http://www.awea.org/smallwind/sagrillo/ms_insur2.html


We’ll need insurance for an “appurtenant structure” and possibly liability insurance (which we already have). From what I’ve read so far, it seems New York State doesn’t allow utilities to require liability insurance.